| Value | ₹235.9 Cr |
|---|---|
| Execution period | Within 60 days from the date of issuance of Work Order/Notice to Proceed (NTP) |
NSE filing, NSE: GKENERGY. Summary written from the filing by ALFA Finder's alert engine.
GK Energy Ltd: key numbers
- Share price
- ₹98.88
- Market cap
- ₹2,005 Cr
- Revenue (annual)
- ₹1,715 Cr
- Net profit (annual)
- ₹204.3 Cr
- P/E (TTM)
- 8.8×Sector 52.2×
- Promoter holding
- 79.20%+0.00% QoQ
- FII holding
- 1.00%Current quarter
Reference market data from a third-party provider, updated daily. Not a valuation or a recommendation.
More from GK Energy Ltd
All →GK Energy Investor Presentation: Key Takeaways
Q2 FY27 standalone revenue ₹4,026.5 Mn (+12.3% YoY), PAT ₹493.6 Mn (+6.3%), EBITDA margin 18.5%. H1 revenue ₹9,078.5 Mn (+38.9%). Scaling rooftop and entering BESS.
GK Energy Merger & Restructuring
GK Energy's board approved incorporating five wholly-owned BESS subsidiaries in the energy sector. All will be 100% owned and subscribed at face value.
GK Energy Results Update
GK Energy reported Q2 FY27 revenue of ₹402.65 Crore and PAT of ₹49.36 Crore with 19,391 systems installed. H1 FY27 PAT grew 30.7% Y-o-Y to ₹109.04 Crore.
GK Energy Q2 FY27 Results: Net Profit ₹49.4 Cr, Up 5.3% YoY
GK Energy Ltd reported revenue from operations of ₹408.7 Cr (+1.2% YoY) and net profit of ₹49.4 Cr (+5.3% YoY) for Q2 FY27.
- Key figure
- Net profit ₹49.4 Cr · +5.3% YoY
GK Energy Board Meeting Date
GK Energy will hold a board meeting on 29 October 2026 to consider unaudited standalone and consolidated results for the quarter ended September 2026. Trading window closes from 1 October to 31 October 2026.
GK Energy Bags ₹330.3 Cr Order from Maharashtra State Electricity Distribution Company Limited
GK Energy received a Rs. 330.29 Crore order from MSEDCL for 14,000 off-grid solar water pumps. Execution is due within 60 days of work order issuance.
- Value
- ₹330.3 Cr
- From
- Maharashtra State Electricity Distribution Company Limited
- Execution
- 60 days from issuance of Work Order/NTP
- Off-Grid Solar Photovoltaic Water Pumping Systems
- 14000 pumps (5 HP)
Other new order win announcements
All →Prime Cable Industries Bags ₹12.98 Cr Order from Reputed listed EPC
Prime Cable Industries received a ₹12.98 Crore purchase order from a listed EPC for LT cable supply. Execution is due in 6 months; no related-party interest.
- Value
- ₹12.98 Cr
- From
- Reputed listed EPC (unnamed)
- Execution
- 6 Months
Siyaram Recycling Industries Bags ₹3.09 Cr Order from Sahjanand Impex
Siyaram Recycling secured a Rs. 3.09 Crore order from Sahjanand Impex for Brass Scrap Honey. Execution is due within 20 days.
- Value
- ₹3.09 Cr
- From
- Sahjanand Impex
- Execution
- Within 20 Days
RailTel Corporation of India Bags ₹22.78 Cr Order from Department Of Posts
RailTel received a Letter of Acceptance from Department of Posts for GPU Compute and Storage services. The Rs. 22.78 Crore order covers a 5-year OPEX execution period.
- Value
- ₹22.78 Cr
- From
- Department Of Posts
- Execution
- 5 years
Dilip Buildcon Bags ₹688.2 Cr Order from National Highways Authority of India
Dilip Buildcon received a Rs. 688.23 Crore LOA from NHAI for a 9.66 km Solapur elevated corridor. Construction spans 24 months with a 15-year operation period.
- Value
- ₹688.2 Cr
- From
- National Highways Authority of India
- Execution
- 24 Months (construction) + 15 years (operation from COD)
- elevated corridor length
- 9.66 km
Jupiter Wagons Bags ₹1,140 Cr Order from Ministry of Railways
Jupiter Wagons secured an order for 2,583 BOXNHL and BOXNS wagons worth ₹1,140 crore from the Ministry of Railways. This reinforces its position in railway rolling stock manufacturing.
- Value
- ₹1,140 Cr
- From
- Ministry of Railways (Railway Board)
ACME Solar Holdings Bags New Order from NTPC Limited
ACME Solar's subsidiary signed a PPA with NTPC for a 400 MW FDRE project. Supply is scheduled to start by June 2028, with a 25-year tenure.
- From
- NTPC Limited
- Execution
- Scheduled Commencement of Supply Date 30.06.2028; project tenure 25 years from SCSD
- FDRE power project contracted capacity
- 400.0 MW